Install 115kV switch at North Gunnison Substation in Colorado.
The U.S. Department of Energy, Western Area Power Administration (WAPA), Rocky Mountain Region, seeks a contractor to install a 115kV switch at the North Gunnison Substation in Colorado. The work includes furnishing all labor, materials, and equipment for the installation of a 115kV circuit switcher, associated structures, and related electrical work. The contractor must have experience with high-voltage substation construction and comply with WAPA's safety and technical standards. The contract is expected to be a firm-fixed-price construction project with a performance period of approximately 120 days. This solicitation is set aside for small businesses under NAICS 237130 (Power and Communication Line and Related Structures Construction).